Traffic & Construction Update – Sicklerville Rd & Erial Rd Roundabout Project
8/18 – 8/20
RE Pierson will demolish the former Wawa building at 4 Erial Road.8:00 AM – 4:00 PM
No traffic impact expected. Work will be contained to the building and parking lot.
8/21 – 8/22
RE Pierson will clear trees along Erial Road for future utility pole relocations. Erial Road CLOSED & detoured 8AM – 4:00 PM.
Traffic Detour - Click Here
Week of 8/25 (8/25 – 8/27)
Kiely Construction(for South Jersey Gas) will begin gas main relocation.
Sicklerville Road CLOSED & detoured 8:00 AM – 5:00 PM.
Traffic Detour - Click Here
9/2 – 9/11
Kiely Construction will have shoulder closures or lane shifts on Erial Road.
8:30 AM – 5:00 PM Minimal traffic impact expected.
Please use caution in the work zones, follow posted detours, and allow extra travel time. Thank you for your patience while these improvements are made.